Project Description

Piner-Olivet Union School District

Construcion Cost:
$15M

School Sites:
New Elementary School: 1

RGM and Associates was the Construction Manager for the new Jack London Elementary School campus in 2003 The first phase of this project was completed more than two months ahead of schedule, allowing the school to occupy the site in time for the fall semester. This was a Financial Hardship project, so it was imperative that the Management Team keep the project on budget. RGM brought Jack London ES in on time and within budget, and has gone on to assist Piner-Olivet with two major modernizations, a new modular building with two classrooms and restroom facilities, and over fifty small modernization and deferred maintenance projects.